Guide

Renovation contracts and change orders in Florida

A clear written contract and a written change-order process protect both the owner and the contractor on a Florida remodel. This guide summarizes several Florida statutes that often come up in home and unit renovation contracts. It is general information, not legal advice, and it is not a description of any one Kirpich contract form. For a written scope on a specific project, call (305) 707-7353 or Get a Free Estimate.

Kirpich, LLC is a Certified General Contractor. We confirm what the project needs and coordinate permits. Kirpich has 15+ years in South Florida remodeling, is rated 5.0 on Google, and covers workmanship with a 1-year workmanship warranty.

Written contracts and notices to the owner

Section 713.015, Florida Statutes, requires a specific lien-law notice in certain direct contracts with a residential property owner when the contract is over $2,500 and covers a one- to four-family dwelling. The notice must be in 12-point bold capital letters and signed and dated by the owner. The point of the notice is that owners understand how construction-lien rights work on their property. Read the statute, and have any contract reviewed if you need legal advice. The exact required wording is in the statute. This is general information, not legal advice.

Section 489.1425, Florida Statutes, requires a written statement about the Construction Industry Recovery Fund in certain residential contracts, unless labor and materials are $2,500 or less. The statute itself is the source for the required language.

A useful contract, aside from those notices, describes the scope of work, the price or the way the price will be calculated, how changes are handled, the payment schedule, and what is excluded.

Deposits, completion and Section 489.126

Section 489.126, Florida Statutes, addresses certain contractor obligations around payments received for construction. Under Section 489.126(2)(a), a contractor who takes more than 10% of the contract price as an initial payment must apply for the permits within 30 days and start work within 90 days after the permits are issued, unless there is just cause or the owner agreed in writing to longer periods. We confirm what the project needs and coordinate permits. This is general information, not legal advice. If you are paying with a loan, see financing vs. paying by milestone.

When a permit may not be required, and when it still is

Section 489.103(7), Florida Statutes, lists certain exemptions from contractor licensing, including limited work an owner may do on a one- or two-family residence built or improved for the owner's own use and not offered for sale or lease (sale or lease within one year is presumed a violation). An exemption from licensing is not the same thing as an exemption from a building permit. Local building departments still decide what needs a permit. We confirm what the project needs and coordinate permits. For local context, see the renovation permits guide for Miami-Dade and Broward.

House Bill 803, as discussed on that permits guide, does not apply to condominium units. Owners of condominium units should plan on association approval and, where required, a permit; Kirpich prepares the condo board paperwork.

Notices of commencement

A notice of commencement is a recorded document often required before work starts on a permitted job. Section 713.13, Florida Statutes, sets out the form and rules: the owner records the notice of commencement before work starts. Section 713.02(5), Florida Statutes, exempts improvements of $2,500 or less. Ask your closing agent, attorney or building department how it applies to your project. This is general information, not legal advice.

Change orders

Most remodeled houses and condominium units uncover something that was not visible at the estimate: hidden water damage, an out-of-level slab, wiring that has to move, or an association comment that changes a finish. A change order is how that new work is described, priced and approved. Extra work should be written down and agreed before it is performed, rather than settled only at the end of the job.

Check the license before you sign

How do you check a contractor's license in Florida? Search the contractor or company name in the Florida Department of Business and Professional Regulation's license search, confirm the license is active and fits the scope, and review any public complaints. Ask for proof of liability and workers' compensation insurance. Under s. 489.128, F.S., a contract entered into by an unlicensed contractor is unenforceable by that contractor. This is general information, not legal advice.

What a written scope should list

Before you compare bids or sign a contract, the written scope should make the job specific enough to price. A useful list includes the rooms and surfaces included; demolition and disposal; cabinets, counters, fixtures and finishes, with allowances called out if they are used; who supplies materials; flooring, paint and transitions; mechanical, electrical and plumbing work; protection of the rest of the home or the building's common areas; and what is excluded. It should also say how changes will be written and approved.

Questions to ask before you sign

Ask how the price is calculated, what the payment schedule is, how allowances are reconciled, and how change orders are written. Ask how permits will be coordinated and who records the notice of commencement. Ask what happens if hidden damage is found once walls or floors are opened. These are general questions for any Florida remodeling contract, not a description of one company's form. If you are budgeting a full-house remodel, see the whole-home renovation cost guide. If you want a walkthrough of how a Kirpich project is organized, see the process section on the homepage.

Work is available across Miami-Dade and Broward. Start with the areas we serve or call (305) 707-7353.

Related pages

Permits guide · Whole-home renovation cost · What affects remodeling cost · Permits & condo approvals · Home renovation

Frequently asked questions

What notices does a Florida residential construction contract often include?

Section 713.015, Florida Statutes, requires a specific lien-law notice in certain direct contracts over $2,500 with a residential owner of a one- to four-family dwelling; the notice must be signed and dated by the owner. Section 489.1425, Florida Statutes, requires a written statement about the Construction Industry Recovery Fund in certain contracts unless labor and materials are $2,500 or less. Read the statutes for the required language. This is general information, not legal advice.

What is a change order?

A change order is a written description of work that was not in the original scope, including its price, agreed before that extra work is performed. Hidden damage, a slab that needs leveling, or an association comment that changes a finish are common reasons for one.

Does a licensing exemption mean I do not need a permit?

No. Section 489.103(7), Florida Statutes, lists certain exemptions from contractor licensing, including limited work an owner may do on a one- or two-family residence for the owner's own use under the conditions the statute sets. That is not the same thing as an exemption from a building permit. We confirm what the project needs and coordinate permits. This is general information, not legal advice; confirm with your building department and association.

Who records the notice of commencement?

Under Section 713.13, Florida Statutes, the owner records the notice of commencement before work starts. Section 713.02(5) exempts improvements of $2,500 or less. Ask your closing agent, attorney or building department how it applies to your project. This is general information, not legal advice.